Project Dashboard

Projects
Project Name Total Bugdet Amount ($) Phase Currently In Status Days Left (%) Complete
High School #6 $147,000,000 Design On Schedule 1066 22 % 
Killeen High School Renovation $99,000,000 Design On Schedule 1066 22 % 
East Ward / West Ward Consolidation $48,000,000 Construction On Schedule 702 26 % 
Clifton Park / Bellaire ES Consolidation $35,000,000 Construction On Schedule 702 26 % 
Pershing Park / Sugar Loaf ES Consolidation $35,000,000 Construction On Schedule 702 26 % 
Elementary School #36 $40,000,000 Design On Schedule 702 0 % 
ADA Renovations $14,750,000 Design On Schedule 318 40 % 
Safety & Security Upgrades $5,250,000 Construction On Schedule 335 43 % 
2017
2018
2019
2020
2021
2022
2023
HS #6
05/22/2018Total Days: 155308/22/2022
KHS Reno
05/22/2018Total Days: 155308/22/2022
EW/WW ES
07/10/2018Total Days: 114008/23/2021
CP/B
07/10/2018Total Days: 114008/23/2021
PP/SL ES
07/10/2018Total Days: 114008/23/2021
ES #36
05/14/2019Total Days: 83208/23/2021
ADA
07/10/2018Total Days: 75608/04/2020
Safety
05/22/2018Total Days: 82208/21/2020
Budget($)
Spent($)
Spent(%)
HS #6 3.85%
KHS Reno 2.03%
EW/WW ES 6.28%
CP/B 5.36%
PP/SL ES 7.10%
ES #36 0.02%
ADA 2.61%
Safety 19.43%